Microsoft Knowledge Base Email Alertz

KBAlertz.com: (88471) - When Microsoft Project encounters a Circular Relationship message, it stops all calculation of the project. Microsoft Project cannot resolve schedule dates for tasks when there is a circular relationship message, so all calculations are stopped until...

Receive Microsoft Knowledge Base articles by E-Mail?

Every night we scan the Microsoft Knowledge Base. If technologies you're interested in are updated, we'll send you an e-mail. You only get one e-mail a day, and only when new articles are added.

Click here to create a
FREE account
Already have an account?
[Click here to Login]

Search KbAlertz

Advanced Search

Webmasters
Put kbAlertz on your website.
[ Click Here for more! ]





ASP.NET 3.5 Web Hosting with Windows 2008 and SQL 2008: Click Here!
Discount ASP.NET Hosting
ASP.NET 2.0 and 3.5
Windows2008 and SQL2008
US and UK Hosting
The ad says 3 - but KBAlertz referrals get
** SIX MONTHS FREE **


Bug Tracking Software
For bug tracking software or defect tracking software or issue tracking software, visit Axosoft.


Community Site



We Send hundreds of thousands of emails using ASP.NET Email



Expert Web Design & Graphic Design
Design44.com

ASP.NET 3.5 Web Hosting with Windows 2008 and SQL 2008: Click Here!
Discount ASP.NET Hosting
ASP.NET 2.0 and 3.5
Windows2008 and SQL2008
US and UK Hosting
The ad says 3 - but KBAlertz referrals get
** SIX MONTHS FREE **




Mentioned In








Microsoft Knowledge Base Article

This article contents is Microsoft Copyrighted material.
©2005-©2007 Microsoft Corporation. All rights reserved. Terms of Use | Trademarks




Article ID: 88471 - Last Review: January 18, 2007 - Revision: 3.1

PRJ: Circular Relationship Stops Calculation

This article was previously published under Q88471

SUMMARY

When Microsoft Project encounters a Circular Relationship message, it stops all calculation of the project.

Microsoft Project cannot resolve schedule dates for tasks when there is a circular relationship message, so all calculations are stopped until the circular relationship is removed.

MORE INFORMATION

Microsoft Project displays the message
Circular relationship in task (number)
when a circular relationship is encountered within a project file.

A message in the status bar of Project also makes reference to the problem. The message reads:
Circular: <project file name>[task number]
To resolve the conflict, follow the successor paths of the task referred to in the message. One of the paths should lead back to the task referenced in the message.

APPLIES TO
  • Microsoft Project 2000 Standard Edition
  • Microsoft Project 98 Standard Edition
  • Microsoft Project 4.1 Standard Edition
  • Microsoft Project 1.0 Standard Edition
  • Microsoft Project 3.0 Standard Edition
  • Microsoft Project 3.0a
  • Microsoft Project 4.0 Standard Edition
  • Microsoft Project 1.1 for Macintosh
  • Microsoft Project 3.0 for Macintosh
Keywords: 
kbprb KB88471
       

Community Feedback System

Very often, it takes hours to solve a problem. Very often, you've looked high and low, and have tried a lot of solutions. When you finally found it, chances are, it was because someone else helped you. Here's your chance to give back. Use our community feedback tool to let others know what worked for you and what didn't.

Please also understand that the community feedback system is not warranted to be correct, it's simply a system that we've built to let people try and help each other. If something in a feedback response doesn't make sense to you, or you're not comfortable making changes that the feedback talks about (like registry edits), please consult a professional.

Thank you for using kbAlertz.com Feedback System.

-- Scott Cate

Be the first to leave feedback, to help others about this knowledge base article.

(Optional) Name

(Optional) Public URL Or Email

Comments
No HTML -- Text Only Please