Task durations are calculated incorrectly if the calendar has non-working times that enclose default non-working times in Microsoft Project Professional 2002
On This Page
SYMPTOMS
If you use Microsoft Project Professional 2002 with Microsoft Project Server, the task durations may be calculated incorrectly when both of the following conditions are true:
- You have an Enterprise Global Calendar that has default non-working times scheduled.
- You apply a new project calendar.
Note Examples of default non-working times are Saturdays and Sundays.
CAUSE
This problem occurs when the new project calendar uses a Copy of Standard calendar that has non-working times defined that enclose the default non-working period.
RESOLUTION
Service Pack Information
This problem is corrected in Project 2002 Service Pack 1.
To resolve this problem, obtain the latest service pack for Project 2002. For additional information, click the following article number to view the article in the Microsoft Knowledge Base:
867829Â
(http://kbalertz.com/Feedback.aspx?kbNumber=867829/
)
How to obtain the latest Microsoft Project 2002 service pack
Hotfix Information
How to Obtain the Hotfix
This issue is fixed in the Microsoft Project 2002 Hotfix Package dated October 6, 2003. For additional information, click the following article number to view the article in the Microsoft Knowledge Base:
829347Â
(http://kbalertz.com/Feedback.aspx?kbNumber=829347/
)
Microsoft Project 2002 Hotfix Package: October 6, 2003
STATUS
Microsoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section of this article.
This problem was first corrected in Project 2002 Service Pack 1.
APPLIES TO
- Microsoft Project 2002 Professional Edition
| kbqfe kbhotfixserver kbtshoot kbproject2002sp1fix kbfix KB830282 |
Community Feedback System
Very often, it takes hours to solve a problem. Very often, you've looked high
and low, and have tried a lot of solutions. When you finally found it, chances
are, it was because someone else helped you. Here's your chance to give back.
Use our community feedback tool to let others know what worked for you and what
didn't.
Please also understand that the community feedback system is not warranted to be
correct, it's simply a system that we've built to let people try and help each
other. If something in a feedback response doesn't make sense to you, or you're
not comfortable making changes that the feedback talks about (like registry
edits), please consult a professional.
Thank you for using kbAlertz.com Feedback System.
-- Scott Cate
Be the first to leave feedback, to help others about this knowledge base
article.
(Optional) Name
(Optional)
Public URL Or Email
Comments
No
HTML -- Text Only Please