Microsoft Knowledge Base Email Alertz

(186093) - In Microsoft Project 98, when you paste tasks or resources in a project, you may receive one of the following error messages. In Windows 95 This program has performed an illegal operation and will be shut down. If the problem persists, contact the...

Search KbAlertz

Advanced Search

Receive Microsoft Knowledge Base articles by E-Mail?

Every night we scan the Microsoft Knowledge Base. If technologies you're interested in are updated, we'll send you an e-mail. You only get one e-mail a day, and only when new articles are added.

Click here to create a
FREE account
Already have an account?
[Click here to Login]











Microsoft Knowledge Base Article

This article contents is Microsoft Copyrighted material.
©2005-©2007 Microsoft Corporation. All rights reserved. Terms of Use | Trademarks

Article ID: 186093 - Last Review: January 23, 2007 - Revision: 1.1

PRJ98: Project Crashes When You Paste Tasks or Resources

This article was previously published under Q186093

On This Page

SYMPTOMS

In Microsoft Project 98, when you paste tasks or resources in a project, you may receive one of the following error messages.

In Windows 95

This program has performed an illegal operation and will be shut down.

If the problem persists, contact the program vendor.
When you click Details, you receive the following error message:
WINPROJ caused an invalid page fault in module WINPROJ.EXE at <address>.

In Windows NT

An application error has occurred and an application error log is being generated.

WINPROJ.EXE
Exception: access violation <number>, Address: <address>.

CAUSE

This problem occurs when the following conditions are true:

The project contains close to the limit of about 7,500 individually formatted cells, or 3,500 individually formatted task bars.
-and-
You paste tasks that have individually formatted cells or bars. Or, you paste resources that have individually formatted cells.

WORKAROUND

To work around this behavior, paste tasks in a view that does not contain formatted cells or bars. For example, create a new Task Sheet view or Resource Sheet view. To create a new view, follow these steps:

  1. On the View menu, click More Views.
  2. Click New, and then click OK.
  3. In the View Definition in <Project Name> dialog box, type a Name for the new view, then pick the type of Screen, Table, and Filter you want to use. Click OK.
  4. Click Apply.
You can now paste tasks safely, because the new view contains no individual bar or cell formating.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, click the article number below to view the article in the Microsoft Knowledge Base:
185102  (http://kbalertz.com/Feedback.aspx?kbNumber=185102/EN-US/ ) PRJ98: How to Obtain and Install MS Project 98 SR-1

APPLIES TO
  • Microsoft Project 98 Standard Edition
Keywords: 
kbbug kberrmsg kbfix KB186093
       

Community Feedback System

Very often, it takes hours to solve a problem. Very often, you've looked high and low, and have tried a lot of solutions. When you finally found it, chances are, it was because someone else helped you. Here's your chance to give back. Use our community feedback tool to let others know what worked for you and what didn't.

Please also understand that the community feedback system is not warranted to be correct, it's simply a system that we've built to let people try and help each other. If something in a feedback response doesn't make sense to you, or you're not comfortable making changes that the feedback talks about (like registry edits), please consult a professional.

Thank you for using kbAlertz.com Feedback System.

-- Scott Cate