Microsoft Knowledge Base Article

This article contents is Microsoft Copyrighted material.
©2005-©2007 Microsoft Corporation. All rights reserved. Terms of Use | Trademarks

Article ID: 182270 - Last Review: January 22, 2007 - Revision: 1.1

PRJ98: Scheduling Error, Task Does Not Split When Linking Tasks

This article was previously published under Q182270

SYMPTOMS

In Microsoft Project 98, when you link tasks, you may receive the following error message:
This action will cause a scheduling conflict. Task <n> of '<project name>' is linked to a task that cannot move, and as a result the link cannot be honored.

You can:

Cancel. Avoid the scheduling confilct.

Continue. Allow the scheduling conflict.
NOTE: <n> is the row number of the task, and <project name> is the name of the project.

If you click Continue and then click OK, the tasks will be linked, but the second task will not be split as expected.

CAUSE

This behavior occurs when you do the following:

  1. You turn off the option Updating task status updates resource status.

    NOTE: To find this option, on the Tools menu, click Options, then click the Calculation tab.
  2. You assign Percent Complete to a task that has a resource assigned.
  3. You turn the option Updating task status updates resource status back on.
  4. You link a task as a predecessor to the task from step 2.

WORKAROUND

To work around this behavior, follow these steps:

  1. Select the two tasks.
  2. On the Edit menu, click Unlink Tasks.
  3. Select the second task.
  4. On the Project menu, click Task Information.
  5. Change the Percent Complete for the task to 0. Click OK.
  6. On the Project menu, click Task Information.
  7. Change the Percent Complete for the task back to the correct value. Click OK.
  8. Select the two tasks.
  9. On the Edit menu, click Link Tasks.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

APPLIES TO
  • Microsoft Project 98 Standard Edition
Keywords: 
kbbug kberrmsg kbnofix KB182270
       

Community Feedback System

Very often, it takes hours to solve a problem. Very often, you've looked high and low, and have tried a lot of solutions. When you finally found it, chances are, it was because someone else helped you. Here's your chance to give back. Use our community feedback tool to let others know what worked for you and what didn't.

Please also understand that the community feedback system is not warranted to be correct, it's simply a system that we've built to let people try and help each other. If something in a feedback response doesn't make sense to you, or you're not comfortable making changes that the feedback talks about (like registry edits), please consult a professional.

Thank you for using kbAlertz.com Feedback System.

-- Scott Cate