Microsoft Knowledge Base Email Alertz

KBAlertz.com: (141654) - In Microsoft Project, when you print a view such as a Gantt Chart, it is possible to print only a selected group of tasks and/or a specific timescale.

Receive Microsoft Knowledge Base articles by E-Mail?

Every night we scan the Microsoft Knowledge Base. If technologies you're interested in are updated, we'll send you an e-mail. You only get one e-mail a day, and only when new articles are added.

Click here to create a
FREE account
Already have an account?
[Click here to Login]

Search KbAlertz

Advanced Search

Webmasters
Put kbAlertz on your website.
[ Click Here for more! ]





ASP.NET 3.5 Web Hosting with Windows 2008 and SQL 2008: Click Here!
Discount ASP.NET Hosting
ASP.NET 2.0 and 3.5
Windows2008 and SQL2008
US and UK Hosting
The ad says 3 - but KBAlertz referrals get
** SIX MONTHS FREE **


Bug Tracking Software
For bug tracking software or defect tracking software or issue tracking software, visit Axosoft.


Community Site



We Send hundreds of thousands of emails using ASP.NET Email



Expert Web Design & Graphic Design
Design44.com

ASP.NET 3.5 Web Hosting with Windows 2008 and SQL 2008: Click Here!
Discount ASP.NET Hosting
ASP.NET 2.0 and 3.5
Windows2008 and SQL2008
US and UK Hosting
The ad says 3 - but KBAlertz referrals get
** SIX MONTHS FREE **




Mentioned In








Microsoft Knowledge Base Article

This article contents is Microsoft Copyrighted material.
©2005-©2007 Microsoft Corporation. All rights reserved. Terms of Use | Trademarks




Article ID: 141654 - Last Review: January 19, 2007 - Revision: 4.1

PRJ: How to Print Specific Tasks from a View

This article was previously published under Q141654

On This Page

SUMMARY

In Microsoft Project, when you print a view such as a Gantt Chart, it is possible to print only a selected group of tasks and/or a specific timescale.

MORE INFORMATION

Selecting Specific Tasks

If there is a common attribute for the desired tasks, you can apply a filter to the view to eliminate tasks that do not satisfy the criteria of the filter. In a task view, for example, the Date Range filter displays only tasks that exist between two specified dates; the Task Range filter shows a block of tasks between two specified ID numbers.

If the tasks to be printed have no common criteria, it is possible to "tag" the desired tasks by setting values in each tasks' Marked field to "Yes." A filter then can be constructed that filters only tasks that have "Yes" in their Marked fields.

NOTE: The "Flag" fields can be used in the same manner as the "Marked" field.

To add the "Marked" field to your table:
  1. Click the column that you want to be to the right of the inserted column (for instance, the Duration column).
  2. On the Insert menu, click Insert Column.
  3. In the Field Name list, click Marked. Click OK.
To create a "Marked Tasks" filter:

  1. On the Project menu in Microsoft Project 98/2000 (or the Tools menu in Microsoft Project versions 4.0 and 4.1), click Filtered For, and then click More Filters.
  2. In the More Filters dialog box, click New.
  3. In the Name field, type "Marked Tasks" as the name for your new filter. Select the "Show In Menu" option.
  4. Under the Field Name column, type "Marked".
  5. Under the Test column, type "Equals".
  6. Under the Values column, type "Yes".
  7. Click OK.
You can now click Apply to run the filter.

To print a specific timescale

Many times, filtering is only the first step to get the desired output. Microsoft Project allows further flexibility to define the printout's date range. To use the date range functions, follow these steps:

  1. On the File menu, click Print.

    The Print command is different from the Print button on the toolbar. The Print command must be used to define the date range.
  2. In the Timescale options, specify a range of dates for your output by typing the start and finish dates in the Dates From and Dates To fields.

    NOTE: Microsoft Project uses the project start date and the project finish date as the default date range, even when you have filtered tasks unless the dates are manually specified as in step 2.

NOTES ON OTHER VIEWS

Calendar View

After applying a filter, it may be necessary to use the Layout Now command on the Format menu to maximize the number of visible tasks. You may be limited in the number of visible tasks by the size of the date boxes in the calendar.

PERT Chart

It is not possible to filter a PERT chart view, nor can a specific timescale be printed. The PERT chart always shows all the tasks that exist in the project.

Resource Graph

Before applying a resource filter, it is necessary to specify how filtered resources will appear in the graph.

  1. On the Format menu, click Bar Styles.
  2. Under Filtered Resources, on the left side, select a style for Overallocated and/or Allocated Resources.
  3. If you like, the individual resources can be shown in the graph relative to the filtered resources or Don't Show can be selected for Resources on the right side of the dialog box.

Sheet Views (Resource Sheet, Task Sheet)

Because these views do not have a timescale, they can only be filtered by the appropriate type of filter.

Resource Usage

These are similar to the Gantt views, except that you must create a resource filter for this view instead of a task filter.

REFERENCES

For additional information, click the following article number to view the article in the Microsoft Knowledge Base:
44582  (http://kbalertz.com/Feedback.aspx?kbNumber=44582/EN-US/ ) PRJ: How to Create an Interactive Filter

APPLIES TO
  • Microsoft Project 2000 Standard Edition
  • Microsoft Project 98 Standard Edition
  • Microsoft Project 4.1 Standard Edition
  • Microsoft Project 4.1a
  • Microsoft Project 4.0 Standard Edition
  • Microsoft Project 4.0 for Macintosh
Keywords: 
kbhowto kbusage KB141654
       

Community Feedback System

Very often, it takes hours to solve a problem. Very often, you've looked high and low, and have tried a lot of solutions. When you finally found it, chances are, it was because someone else helped you. Here's your chance to give back. Use our community feedback tool to let others know what worked for you and what didn't.

Please also understand that the community feedback system is not warranted to be correct, it's simply a system that we've built to let people try and help each other. If something in a feedback response doesn't make sense to you, or you're not comfortable making changes that the feedback talks about (like registry edits), please consult a professional.

Thank you for using kbAlertz.com Feedback System.

-- Scott Cate

Be the first to leave feedback, to help others about this knowledge base article.

(Optional) Name

(Optional) Public URL Or Email

Comments
No HTML -- Text Only Please