Microsoft Knowledge Base Email Alertz

KBAlertz.com: (113759) - In Microsoft Project, when you move a task to start after the project finish date, the Late Start and Late Finish dates for the task are calculated incorrectly if the project is scheduled from the project finish date.

Receive Microsoft Knowledge Base articles by E-Mail?

Every night we scan the Microsoft Knowledge Base. If technologies you're interested in are updated, we'll send you an e-mail. You only get one e-mail a day, and only when new articles are added.

Click here to create a
FREE account
Already have an account?
[Click here to Login]

Search KbAlertz

Advanced Search

Webmasters
Put kbAlertz on your website.
[ Click Here for more! ]





ASP.NET 3.5 Web Hosting with Windows 2008 and SQL 2008: Click Here!
Discount ASP.NET Hosting
ASP.NET 2.0 and 3.5
Windows2008 and SQL2008
US and UK Hosting
The ad says 3 - but KBAlertz referrals get
** SIX MONTHS FREE **


Bug Tracking Software
For bug tracking software or defect tracking software or issue tracking software, visit Axosoft.


Community Site



We Send hundreds of thousands of emails using ASP.NET Email



Expert Web Design & Graphic Design
Design44.com

ASP.NET 3.5 Web Hosting with Windows 2008 and SQL 2008: Click Here!
Discount ASP.NET Hosting
ASP.NET 2.0 and 3.5
Windows2008 and SQL2008
US and UK Hosting
The ad says 3 - but KBAlertz referrals get
** SIX MONTHS FREE **




Mentioned In








Microsoft Knowledge Base Article

This article contents is Microsoft Copyrighted material.
©2005-©2007 Microsoft Corporation. All rights reserved. Terms of Use | Trademarks




Article ID: 113759 - Last Review: November 30, 2006 - Revision: 4.4

Incorrect Late Start and Late Finish dates when you move a task in Project

This article was previously published under Q113759

SYMPTOMS

In Microsoft Project, when you move a task to start after the project finish date, the Late Start and Late Finish dates for the task are calculated incorrectly if the project is scheduled from the project finish date.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.

MORE INFORMATION

When you move a task to start after the project finish date, and the project is scheduled from the project finish date, the task is scheduled after the project finish. This behavior is expected. However, the Late Start and Late Finish dates for the task are the same as the scheduled start and finish. This behavior is incorrect because the task cannot start or finish after the project finishes; therefore, the task should appear with negative slack.

Note that this behavior does not occur in Microsoft Project version 3.0.

APPLIES TO
  • Microsoft Office Project Professional 2007
  • Microsoft Office Project Standard 2007
  • Microsoft Office Project Professional 2003
  • Microsoft Office Project Standard 2003
  • Microsoft Project 2002 Professional Edition
  • Microsoft Project Standard 2002
  • Microsoft Project 2000 Standard Edition
  • Microsoft Project 98 Standard Edition
  • Microsoft Project 4.1 Standard Edition
  • Microsoft Project 4.1a
  • Microsoft Project 4.0 Standard Edition
  • Microsoft Project 4.0 for Macintosh
Keywords: 
kbtshoot kbpending kbusage KB113759
       

Community Feedback System

Very often, it takes hours to solve a problem. Very often, you've looked high and low, and have tried a lot of solutions. When you finally found it, chances are, it was because someone else helped you. Here's your chance to give back. Use our community feedback tool to let others know what worked for you and what didn't.

Please also understand that the community feedback system is not warranted to be correct, it's simply a system that we've built to let people try and help each other. If something in a feedback response doesn't make sense to you, or you're not comfortable making changes that the feedback talks about (like registry edits), please consult a professional.

Thank you for using kbAlertz.com Feedback System.

-- Scott Cate

Be the first to leave feedback, to help others about this knowledge base article.

(Optional) Name

(Optional) Public URL Or Email

Comments
No HTML -- Text Only Please