Mentioned
In
|
 |
 |
 |
 |
Microsoft Knowledge Base Article
This article contents is Microsoft Copyrighted material.
©2005-©2007 Microsoft Corporation. All rights reserved. Terms
of Use |
Trademarks
Article ID: 113447 - Last Review: January 18, 2007 - Revision: 3.1 PRJ: Scheduling a Project Based on a Task Start DateThis article was previously published under Q113447 On This PageSUMMARY
If you want a project's start and finish dates to be calculated based on
the date for a particular task that occurs in the middle of the project
(for example, if you have a task that requires a delivery of material
before the task can begin, and you would like the entire project start and
finish dates to be calculated around this delivery date), you can do so by
manipulating the Schedule From option in the Project Info form.
MORE INFORMATION
To schedule a project around a task in the middle of the project, follow
the appropriate procedure below.
Microsoft Project 98/2000- On the Project menu, click Project Information.
- In the Schedule From list, select Project Start Date,
and then click OK.
The project start date will default to the current date. - Enter all task descriptions and durations, and establish appropriate
relationships between the tasks. Do not assign any resources at this
time.
- Select the task that has the known start date.
- On the Project menu, click Task Information, and then
click the Advanced tab.
- Under Constrain Task, in the Task list, select Must
Start On. In the Date box, type a date or click the arrow
to select a date on the calendar. Click OK.
At this point, Microsoft Project calculates the project's finish
date. If the date you entered was earlier than the date originally
calculated, you will receive a warning stating "Late date before
scheduled date...." Click OK. - On the Project menu, click Project Information.
- In the Schedule From list, click Select Project Finish
Date, and then click OK.
This step will calculate the new project start date. - On the Project menu, click Project Information.
- In the Schedule From list, click Project Start Date,
and then click OK.
The start and finish dates for your project will be based on the start date
you specify for a particular task. If Microsoft Project has to recalculate
the schedule in the future, change the constraint for that task from Must Start On to Start No Earlier Than, and use the same date.
Once this has been done, resources can be assigned and the schedule can be
altered as needed
Microsoft Project Version 4.x- On the File menu, click Summary Info.
- In the Schedule From list, click Project Start Date,
and then click OK.
The project start date will default to the current date. - Enter all task descriptions and durations, and establish appropriate
relationships between the tasks. Do not assign any resources at this
time.
- Select the task that has the known start date.
- On the Insert menu, click Task Information, and then
click the Advanced tab.
- Under Constrain Task, in the Type list, click Must
Start On. In the Date box, type a date or click the arrow
to select a date on the calendar. Click OK.
At this point, Microsoft Project calculates the project's finish
date. If the date you entered was earlier than the date originally
calculated, you will receive a warning stating "Late date before
scheduled date...." Click OK. - On the File menu, click Summary Info.
- In the Schedule From list, click Project Finish Date,
and then click OK.
This step will calculate the new project start date. - On the File menu, click Summary Info.
- In the Schedule From list, click Project Start Date,
and then click OK.
The start and finish dates for your project will be based on the start date
you specify for a particular task. If Microsoft Project has to recalculate
the schedule in the future, change the constraint for that task from Must Start On to Start No Earlier Than, and use the same date.
Once this has been done, resources can be assigned and the schedule can be
altered as needed.
Microsoft Project Versions 3.0a and Earlier- On the Options menu, click Project Info.
- Select Start under Schedule Project From, and then
click OK. The project start date will default to the current
date.
- Enter all task descriptions and durations, and establish appropriate
relationships between the tasks. Do not assign any resources at this
time.
- Select the task that has the known start date.
- On the Edit menu, click Task Form.
- In the Task Form, change the constraint to Must Start
On and enter the date in the Date field. Click OK.
At this point, Microsoft Project calculates your new project finish
date.
NOTE: If the date you entered was earlier than the date
originally calculated, you will receive a warning stating "Late date
before scheduled date...." Click OK. - On the Options menu, click Project Info.
- Select Finish under Schedule Project From, and then
click OK.
This step will calculate your new project start date. - From the Options menu, choose Project Info
again.
- Select Start under Schedule Project From, and then
choose OK.
APPLIES TO- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
- Microsoft Project 1.0 Standard Edition
- Microsoft Project 3.0 Standard Edition
- Microsoft Project 3.0a
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 1.1 for Macintosh
- Microsoft Project 3.0 for Macintosh
Community Feedback System
Very often, it takes hours to solve a problem. Very often, you've looked high
and low, and have tried a lot of solutions. When you finally found it, chances
are, it was because someone else helped you. Here's your chance to give back.
Use our community feedback tool to let others know what worked for you and what
didn't.
Please also understand that the community feedback system is not warranted to be
correct, it's simply a system that we've built to let people try and help each
other. If something in a feedback response doesn't make sense to you, or you're
not comfortable making changes that the feedback talks about (like registry
edits), please consult a professional.
Thank you for using kbAlertz.com Feedback System.
-- Scott Cate
Be the first to leave feedback, to help others about this knowledge base
article.
(Optional) Name
(Optional)
Public URL Or Email
Comments
No
HTML -- Text Only Please
|
 |
 |
 |
 |
 |
 |
 |
| |